Traffic Engineering Implemented on Jalan Muara Baru
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
The Jakarta Transportation Agency is carrying out traffic engineering on Jalan Muara Baru, North Jakarta, in connection with the work of placing drinking water pipes at that location.
Avoid these road sections
Head of Jakarta Transportation Agency, Budi Awaluddin said the work site is located near the Muara Baru Sub-Sector Police Station. Therefore, to support the work, traffic engineering will be implemented according to the work stages.
Traffic Engineering Implemented Under Pesing Flyover to Ease CongestionHe added that mobilization of materials and heavy equipment will only be carried out at night, between 10 PM up to 4 AM. In addition, uniformed officers from the project will be deployed to assist with traffic control.
"We urge road users to avoid these road sections and to adjust to the established traffic arrangements, obey traffic signs, instructions from officers and prioritize road safety," he said, Friday (11/13).
The following is traffic engineering according to the work stages:
Phase 1
1) Hot tapping of 600mm pipe
2) Implementation period: November 7-27, 2026
3) Work will be carried out on the east side of Jalan Muara Baru (occupying one lane) with a work area of 5.1 meters and a road width of 5.6 meters.
4) Traffic will use the west side lane with a contraflow lane.
Phase 2
1) Chamber tank work
2) Implementation period: November 28-December 23, 2026
3) The work will be located in front of the Muara Baru Sub-sector Police Station, with a work area measuring 2.4 meters with a 4.5 meter margin.